Renewal of the Coarse and Fine Processing Systems At the Großefehn site of MKW – Materialkreislauf- und Kompostwirtschaft GmbH & Co. KG in the district of Aurich, the coarse and fine processing systems of the composting and anaerobic digestion plant were renovated. The plant consists of a coarse processing system for the delivered biowaste and … find out more

Conversion of a windrow composting facility This year, a windrow composting facility was commissioned that had been modernized through the addition of active aeration and a semi-permeable membrane. The modernization became necessary for reasons of emission control. The applied process minimizes emissions, particularly odors: the membrane retains them, while microorganisms in the composting material biologically … find out more

As 2025 comes to a close, we look back with gratitude on a successful 12 months. Not least, the positive and constructive exchange within the framework of our cooperation has led to successful projects. We look forward to staying in touch with you in the coming year so that we can initiate new projects together … find out more

At MKW – Materialkreislauf- und Kompostwirtschaft GmbH & Co. KG, the first PV system at the site went into operation in mid-November on the roof of the West Hall. A total of 752 modules have been generating green electricity for plant operation ever since. pbo supported the project from the outset with a profitability analysis … find out more

At the end of the year, we would like to thank you for your trusting cooperation. The open exchange and joint projects have made 2024 a successful year. We look forward to 2025 with optimism and look forward to working together on existing projects in the areas of the circular economy and renewables and taking … find out more

The RSAG (Rhein-Sieg-Abfallwirtschaftsgesellschaft) had earlier replaced the roof of one of its halls with a Photovoltaic (PV) system. Due to damages and wear and tear, the 4,236 modulesof the old PV system need to be replaced. Thanks to technological progress, the number of modules could be reduced to 570 while maintaining the same total output, … find out more

The soil treatment plant in Wuppertal is currently in the construction phase. Mohan Karakoc has implemented our current planning in a great visualisation. Together with our client AWG Abfallwirtschaftsgesellschaft mbH Wuppertal in collaboration with WSW Wuppertaler Stadtwerke GmbH, we are looking forward to the upcoming commissioning phase.

pbo has been entrusted with the general planning services for the bottom ash processing plant at the Ingolstadt site since the 3rd quarter of 2023. pbo is providing the services of the general planner. The project and specialist planning includes buildings and interiors, engineering structures, outdoor facilities, structural planning and technical equipment. Service phases 1 … find out more

At the end of 2023, AWA Entsorgung GmbH commissioned the engineering company pbo with the general planning of the fermentation and composting plant at the Würselen site. As general planner, pbo is dealing with the issues in connection with the service categories §43 HOAI Civil Engineering Structures, §51 HOAI Structural Engineering and §55 HOAI Technical … find out more

pbo wins the engineering competition and starts planning a recycling center in Velbert for Technische Betriebe Velbert AöR. The new replacement building for the Velbert recycling center is being built on an area of up to 7,050 m². pbo is providing the services of the general planner. The project and specialist planning includes buildings and interiors, … find out more